(1) in stage lighting power cable and signal wiring and connector construction initially completed, dimming equipment and lighting installation.
(2) according to the order of the construction by Taiwan will adjust the light equipment into the construction site, in order to ensure the quality of equipment installation, equipment unpacking inspection program after the implementation, in accordance with the design
Technical documentation provided by the parameters of electrical, mechanical performance testing, and then install the equipment.
(3) equipment installation process with civil, ventilation, air conditioning, water supply and drainage, electricity, decoration and other professional work closely with, according to the construction progress of the building
Arrangements for electrical engineering construction, in the decoration process, and actively cooperate with the decoration unit, the installation position of the switch is set aside to avoid the installation of the installation
Built into damage.
(4) in the process of construction of building walls, floor, indoor roof, outside the building top slot, punctured to take strict measures to protect, the construction should be promptly restored.
(5) on the wall, the floor leaving holes, in addition to the design requirements, the rest should be in the pipeline construction is completed, with the construction of the hole sealing or fire Isolation.
(6) for the sake of the full, the light and the box shall be fitted to the rear of the site for the installation of the lamp.
(7) all the lamps on the electric system installation, must have relevant construction units to assist control. |